GRP Installation on ETP Tank Floor with Wall Patchwork, Almarai Abu Dhabi

Project Overview

Client: Almarai Drinks Manufacturing LLC
Location: Kizad, Abu Dhabi
Contact Person: Shamsudheen (Project Manager)
Start Date: 06 October 2022
End Date: 10 October 2022
Area: 126 m2 (Walls and Floor of ETP MBR Tank)

This project involves the waterproofing using GRP lining and the repairing of an Effluent Treatment Plant (ETP) tank at Almarai’s Water Treatment Plant.

Findigs

  • Blistering, bulging, and GRP delamination on walls.
  • The newly poured concrete floor required GRP lamination.

Risks

  • The ETP tank was 5 meters high and involved confined space entry.

Solution

  • Patchwork was done where the old GRP was defective.
  • Vinyl ester GRP is applied to the walls and floor.
  • The final finish included proper sanding and gel coat.

More Projects Like This

Ready to Talk?

Do you need waterproofing support for a similar issue? Contact us for a free inspection within 24 hours.

GRP Installation on ETP Tank Floor with Wall Patchwork, Almarai Abu Dhabi