Project Overview
Client: Block on Block Building Contracting LLC
Location: Nad Al Sheeba, Dubai, UAE.
Contact Person: Mr. Jestoni Estaura
Start Date: 19 Nov 2024
End Date: 25 Nov 2024
Area: 135 m2 (10 Manholes & 5 UG Water Tanks)
Application of 4mm thick GRP lining inside manholes and underground water tanks across five residential villas.
Solution
- Surface preparation involved cleaning and removing any dust or debris that could hinder the bonding process.
- GRP was applied seamlessly to all internal tank and manhole surfaces.
- Project completed with a consistent finish and long-term sealing performance.